Past Work – Case Studies
CNRL
Module Fabrication and Assembly for Kirby North 19A Tank Farm
DESCRIPTION:
Gemini’s relationship with CNRL was transparent and collaborative. We worked together to ensure the best project outcomes for this modules project.
SCOPE:
Fabrication and Assembly of 14 Modules and 4 Ship Loose Pipe packages, including Electrical, Instrumentation and Insulation
STATS:
- Project Start: September 2017
- Project Completion: May 2018
- Duration: 7 months
- Safety @ Completion: 0 First Aid / 0 LTI / 0 TRIF / 1 Medical / 1 Modified Duty / 1 Near Miss
- Weld Repair Percentage @ Completion: 1.7%
- Total FDI: 28,912 FDI
- Total LM Pipe: 7080 LM Installed (+ Hydro of Ship Loose Pipe spools)
- Total KGs Steel: 586,507 KGs Fabricated and Erected
- Total EHT: 11,667 LM
- Total Cable: 3081 LM (+ 2442 LM Cable Tray)
- Total Insulation: 4129 LM (+ 397 soft covers)