CNRL

Module Fabrication and Assembly for Kirby North 19A Tank Farm

DESCRIPTION:

Gemini’s relationship with CNRL was transparent and collaborative. We worked together to ensure the best project outcomes for this modules project. 

SCOPE:
Fabrication and Assembly of 14 Modules and 4 Ship Loose Pipe packages, including Electrical, Instrumentation and Insulation

STATS:

  • Project Start: September 2017
  • Project Completion: May 2018
  • Duration: 7 months
  • Safety @ Completion: 0 First Aid / 0 LTI / 0 TRIF / 1 Medical / 1 Modified Duty / 1 Near Miss
  • Weld Repair Percentage @ Completion: 1.7%
  • Total FDI: 28,912 FDI
  • Total LM Pipe: 7080 LM Installed (+ Hydro of Ship Loose Pipe spools)
  • Total KGs Steel: 586,507 KGs Fabricated and Erected
  • Total EHT: 11,667 LM
  • Total Cable: 3081 LM (+ 2442 LM Cable Tray)
  • Total Insulation: 4129 LM (+ 397 soft covers)