Skip to main content

Past Work – Case Studies

Fluor Fort Hills

Module Assembly for Fort Hills Energy LP Utilities Project

SCOPE:

Assembly, E&I and Insulation of seventeen (17) Modules  

STATS:

  • Project Start: February 2016
  • Project Completion: August 2016
  • Duration: 7 Months
  • Safety @ Completion: 0 TRIF/0 LTI/0 Medical/2 Property Damage/1 Near Miss
  • Weld Repair @ Completion: 1.89%
  • Total FDI: *Tie in welds only (supplied spools) 6887 FDI
  • Total LM Pipe: 2825 LM
  • Total KGs Steel: 746,577 KGS
  • Total EHT: 3546 LM
  • Total Cable: 6380 LM (1263 LM tray) 
  • Total Insulation: 2125 LM, 8 Pieces of Equipment (vessels), Soft Covers